National Audit Office

Key activities included:

  • Initial full site investigation and survey plan including visual inspection, bulk sampling and assessment of possible extent and location of asbestos containing materials (ACMs).
  • Full Refurbishment and Demolition survey of all areas of the building (13 floors, plant rooms, voids, basement, sub-basement and lift shafts).
  • Development of project strategic plan for asbestos remediation phase including projected cost implications.
  • Development of specification for the asbestos remediation phase of works.
  • Project supervision and analytical attendance during the remediation phase including issue of re-occupation certificates and project completion file.
  • Issue of revised and updated asbestos register and site specific asbestos management plan.
  • Delivery of project specific asbestos related training to site based stakeholders.

Working in partnership with all stakeholders and ensured the identification of asbestos containing materials and its subsequent safe remediation enabling the construction phase to be completed effectively.